Deliveries of the Flight Models of the french participations

  • Deliveries of the FM of the french participations to SPIRE instrument
    • SMECm (FTS spectrometer mechanism) delivered in July 2006
    • Warm Electronics (DCU + FCU) delivered in March 2006
    • Spectrometer and the photometer optics delivered in November 2004

  • Deliveries of the FM of the french participations to PACS instrument
    • Warm Electronics (BOLC) delivered in August 2006
    • Photometer Focal Plane Unit (PhFPU) delivered in July 2006
    • Two focal planes bolometer arrays delivered in June 2006
    • Cryo cooler delivered in August 2005

  • Deliveries of the FM of the french participations to HIFI instrument
    • High Resolution Spectrometer HRS delivered in August 2006
    • Mixer band 1 delivered in May 2005